A company spends 5 million yuan on research. For tax purposes it deducts 10 million. At the 25% corporate rate — the standard rate covered in China corporate income tax rates — that is 1.25 million of tax saved on 5 million of spend — a 25% subsidy delivered through the tax return rather than through a grant application.

That is the Chinese R&D super deduction, and unlike most incentives in this system it has no expiry date. Announcement No. 7 of 2023 raised the rate to 100% and stated that it operates as a long-term institutional arrangement. It is not one of the reliefs that needs re-checking every December for a renewal notice.

What it does need is evidence. The deduction is refused more often for missing paperwork than for ineligible spending, and the paperwork requirement is specific.

Who can claim

Three conditions, all administrative rather than strategic:

  • The taxpayer must be a resident enterprise — which includes wholly foreign-owned enterprises and joint ventures. A branch of a foreign company is not a resident enterprise and cannot claim.
  • Accounting must be sound and the enterprise must be assessed on an audit basis rather than by deemed assessment.
  • R&D expenditure must be accurately separable from production and operating costs.

Note what is absent: there is no size threshold, no sector encouraged-list, no minimum spend. A twenty-person software company claims on the same terms as a listed manufacturer. This is a different structure from the small-enterprise rate, which does turn on size — that regime is covered in the 5% rate for small low-profit firms.

The six excluded industries

The exclusion is by industry, not by activity. Six sectors are outside the regime entirely, regardless of how much genuine research they do:

Tobacco manufacturing; accommodation and catering; wholesale and retail; real estate; leasing and business services; entertainment.

The list comes from Caishui [2015] No. 119 and can be extended by the finance and tax authorities. The exclusion is determined by the enterprise's main business — the sector contributing the largest share of revenue — so a technology company with a small trading division is fine, while a trading company with a small technology division is not.

How the deduction works

The treatment splits on whether the spending produced a capitalisable asset.

Expensed (no intangible formed)Capitalised (intangible formed)
Base deductionActual amountAmortisation of cost
Additional deduction100% of actual amount100% of amortisation
Total relief200% of spend, in year one200% of cost, over the amortisation period

Concretely: 5 million of expensed research produces a 10 million deduction in that year. Ten million capitalised and amortised over ten years produces 2 million of deduction each year — 1 million of accounting amortisation plus 1 million of additional deduction.

The 2023 change applies to intangibles whenever formed. An intangible recognised in 2022 under the old 75% regime is amortised at 200% of cost for the remainder of its life. Companies that assumed the old rate was locked in for existing assets should recheck their schedules.

What counts as R&D

This is where most claims fail on substance rather than on paperwork. The activity must be systematic work with a defined objective, aimed at new scientific or technical knowledge, creative application of it, or a substantive improvement to technology, product or process.

Seven categories are explicitly excluded:

  1. Routine upgrading of existing products or services.
  2. Direct application of research results — adopting a published process, material or design as-is.
  3. Technical support provided to customers after commercialisation.
  4. Repeated or trivial changes to existing products, services, technology, materials or processes.
  5. Market research, efficiency studies, or management studies.
  6. Routine quality control, testing and analysis, repair and maintenance carried out as part of the production or service process.
  7. Research in social sciences, arts or humanities.

Two of these account for a large share of disallowed claims in practice. Routine upgrading is the commonest: a version bump, a cosmetic redesign, a performance tweak that any competent engineer would make. And post-sale technical support is frequently booked to R&D because the engineers doing it are the same engineers — but the activity is customer service, not research.

Counter-intuitively, failure does not disqualify the spend. STA Announcement No. 40 of 2017 confirms that research which produces no usable result still qualifies, provided the activity itself met the definition. A project that was abandoned after eighteen months is a legitimate claim; the absence of an output is not evidence that there was no research.

What goes into the cost base

STA Announcement No. 40 of 2017 sets six categories:

CategoryIncludes
PersonnelWages, salaries and social insurance for staff directly engaged in R&D; fees to externally engaged researchers
Direct inputsMaterials, fuel and power, tooling and moulds, prototypes, testing consumables, equipment rental
DepreciationInstruments and equipment used for R&D
Intangible amortisationSoftware, patents and licences used for R&D
Design and testingNew product design, new process specification, clinical trials, field testing
Other related costsTechnical literature, translation, expert consultation, IP filing and registration, travel and conferences

The sixth category carries a cap: other related costs may not exceed 10% of total qualifying R&D expenditure. A company that loads travel, conference and consultancy into the R&D pool will find the excess disallowed in full, and the arithmetic is done on the aggregate rather than project by project.

One more adjustment: scrap, defective output and intermediate test products generated during research must be netted off the R&D cost. Where a pilot line sells its trial output, the proceeds reduce the claimable base.

Commissioned and collaborative research

Outsourcing does not preserve the full deduction:

  • Domestic commission. Only 80% of the amount actually paid enters the commissioning party's R&D base. The party performing the work cannot claim on the same expenditure.
  • Overseas commission. Also 80%, and capped: the claimable overseas amount may not exceed two-thirds of qualifying domestic R&D expenditure.
  • Joint development. Each party claims on its own share of the cost.

Worked through: a company with 3,000,000 of qualifying domestic R&D pays a foreign laboratory 1,500,000. The overseas cap is 3,000,000 × 2/3 = 2,000,000. At 80%, the claimable overseas amount is 1,200,000, which sits under the cap, so all of it qualifies — giving a total base of 4,200,000 and an additional deduction of the same amount.

Had the overseas spend been 3,000,000, the 80% figure would be 2,400,000 against a 2,000,000 cap, and 400,000 would be permanently lost.

The auxiliary ledger

This is the single most common reason a valid claim collapses.

The rules require a project-by-project auxiliary ledger recording the R&D expenditure attributable to each project, prepared under the format in STA Announcement No. 97 of 2015 or the 2021 revision. Where R&D and production costs are not separately accounted for, and cannot be clearly divided, no deduction is allowed at all — not a reduced one.

The pattern that fails is familiar: a company runs genuine research, books the engineers' salaries into a single cost centre alongside production support, and at year end asks its auditor to reconstruct the split. That reconstruction is exactly what the rule does not accept. The ledger has to exist as the spending happens.

The ledger is the claim, not the evidence of it. Chinese practice treats the auxiliary ledger as constitutive rather than corroborative. A taxpayer with excellent engineers, genuine projects and a fully defensible technical case will still lose the entire deduction if the cost split was never recorded at the time. This is the opposite of how most jurisdictions handle substantiation, and it is the single point where well-run R&D programmes most often fail — not because the research was ineligible, but because nobody told the finance team to open a separate ledger in January.

Where companies get it wrong

  • Treating routine upgrades as R&D. The most frequent substantive adjustment.
  • No project-level ledger, or one built retrospectively at year end.
  • Pooling R&D and production staff in the same cost centre, so the split cannot be evidenced.
  • Forgetting the 10% cap on other related costs — the excess is disallowed, not scaled back.
  • Claiming 100% of commissioned research instead of 80%.
  • Missing the two-thirds overseas cap, which silently strands part of the spend.
  • Not netting off scrap and trial output sold during the project.
  • Assuming the old 75% rate still applies to intangibles formed before 2023. It does not.

Sources and current status

  • MOF and STA Announcement No. 7 of 2023 — 100% additional deduction for expensed R&D and 200% amortisation for capitalised R&D, effective 1 January 2023 and stated to be a long-term institutional arrangement.
  • Caishui [2015] No. 119 — policy scope and management requirements, including the six excluded industries and the accounting separation rule.
  • STA Announcement No. 40 of 2017 — cost categories, the 10% cap on other related costs, treatment of failed projects, and the netting-off of residual output.
  • STA Announcement No. 97 of 2015 — the auxiliary ledger format, still available alongside the 2021 revision.
  • Caishui [2018] No. 64 — commissioned overseas research and the two-thirds cap.

Status note. Unlike the small-enterprise rate and the VAT reliefs, this one has no end date in the instrument itself — a point worth making to a board that has been told all China incentives are temporary. The definitions and the documentation requirements, however, are where claims actually fail, and they have been stable since 2017 precisely because they are the enforcement mechanism.

This is a plain-English reference, not tax advice. Whether a particular development activity qualifies is a judgement that turns on project records and engineering facts. Confirm with a licensed practitioner before filing, and build the ledger before the spend, not after.